Preparation
A preliminary phase was carried out in collaboration with Verhaert from January 2026 to September 2026. What took place during that preliminary phase?
- Research was conducted into the reliability of the pipe auger, with particular attention paid to hydraulic instability during overfilling and full submersion.
- Technical issues from previous installations (including those in Deurne and Veurne) were objectively analysed.
- Knowledge was built up through desk research, literature reviews and workshops with hydraulic and electromechanical experts.
- Various stakeholders were involved, including the Department of Infrastructure and the Environment (MOW), the Hydraulic Engineering Laboratory, the Province of West Flanders, Westkustpolder and Verhaert.
- The research needs were then tested against the market via an international market consultation.
- A dialogue was initiated with European screw manufacturers, contractors/integrators and CFD centres of expertise.
The preliminary phase provided greater insight into the causes of the technical phenomena and possible solutions.
On this basis, various research and development (R&D) scenarios were assessed for feasibility prior to the tender process.
The final report containing the insights gained is now publicly available.