Implementation
In October 2023, the contract was awarded to Viktor Goes Green BV.
The project will be carried out in several successive phases:
- Analysis – Converting the woody fraction into high-quality biochar and proposing drying techniques tailored to wood chips and fibres
- Design of the entire pilot plant
- Tendering and construction of the pilot plant
- Commissioning / Test phase
- Commercial phase and maintenance
The first and second phases have been successfully completed. The third phase is currently underway.
Read the article published on the VRT NWS website on 9 March 2026.